BACK LOBBY (service entrance)

We will be gilding 2 half “bays” where the painters previously damaged the ceiling by using tape near the wall. Below are photos of one of the 2 bays, on the East side, adjacent to main lobby. The West bay we can reach with a double high tower, 5 ft wide.

Accord needs to build a platform to extend the “roof” of the room both length wise, above the doors (see yellow arrow) and width wise.

The platform needs to come out another foot at least width wise so that we can stand on it safely with ladders.

Length of platform from wall to wall: approx. 15 ft.

This platform needs to be built before we start the gilding, since this is the area we do first, before the main lobby.

Back_Lobby3 copyThe platform needs a railing as well.

. Back_Lobby2 Back_Lobby4

___________________________________________

MAIN LOBBY front area

ACCORD WILL SUPPLY:

         EVERY WEEKEND:

  • 2 Rolling towers, each 5 ft wide, 12 ft high, blue frames, with railings and outriggers.
  • Accord will set these up each weekend Saturday mornings before 9 AM, and take them down Monday mornings before 8.

FIRST WEEKEND:

  • Platform for East area of back lobby, to extend the “roof” of the room both length wise, above the doors and width wise.

The platform needs to come out another foot at least width-wise, so that we can stand on it safely with ladders. This platform needs to be built before we start the gilding, since this is the area we do first, before the main lobby.

LAST WEEKEND:

  • Bridge / planks for the main lobby. Bridge between the 2 towers (when working on the front ceiling panel at the entrance door). This bridge needs to be safe, with railing.

Bridge & towers need to be installed before Saturday 9 AM. Taken down Monday morning early.

The area next to the front entrance (on the main lobby side), cannot be reached in the middle section by rolling towers. The round entrance door is in the way.

 

Front Front2